KMC area ma 2.5 talla ghar banaune. Naksa pass process kasto cha?
Naksa pass (building permit) Kathmandu Metropolitan ma kati samaya lagcha?
Asked 19d ago2 answers
11
✅ Best answer, chosen by the person who asked
11
In KMC it's done through the e-BPS (electronic building permit system): a registered engineer/consultant submits the drawings online, then site inspection, then permit for plinth, then superstructure approval after plinth check, then completion certificate.
Time depends on documents and inspection queue, plan for a few months, not weeks. Use a consultant who regularly files in KMC, they know the current checklist.
2 Answers
4
Ghar ko design ma setback ra ground coverage rule follow garnus, natra completion certificate (nirman sampanna) paudaina ra pachi bank loan ma problem.